If you want to avoid that two oders are running the same time in different job chains you have two options.
- Merging the two job chains into one and set the attribute max_orders=1. See jobchain34 in the example file. Please start order part3 and then try to start order part4 while part3 is running.
- Using semaphores
Achiving this you have to create a job for entering the critical section. This job sets a semaphore. If free sets the semaphore and enters the critical section (the job chain). If not, a wair will be invoked. This job is the first job in the job chain.
Then you need a job for leaving the critical section. This job unsets the semaphore.
As a semaphore you can use a file (then setting is creating the file, checking is file existing and leaving is deleting the file) or a event or someting else.
Please note that it is important to execute the leave_critical_section job To unset the semaphore also in case of an error the error node should not only be an endstate but a node with the leave job.
You find an example in the example file with jobchain3 and jobchain4. This example creates files to set/unset the semaphore for the critical section.
Here is the download link for the semaphore example. Please note that the scripts are running with windows os.