Question:

If I have a stand-alone job set to run every 30 minutes, what will happen if that job is still running after 30 minutes? What I need to happen is that the job will just continue to run and will not start again until it is complete.

Answer:

The simplest approach here is to set either the repeat or absolute_repeat attributes for the JobScheduler period element.

...