  • A given workflow A starts workflow B by use of using the JS7 - AddOrder Instruction.
  • Workflow B runs asynchronously and in parallel to workflow A.
  • Workflow A should wait for completion of workflow B.

...

  • The workflow executes a number of jobs and an JS7 - AddOrder Instruction for workflow B.
  • Starting from the AddOrder Instruction workflow B runs asynchronously and in parallel.
  • Subsequently a JS7 - ExpectNotice ExpectNotices Instruction makes workflow A wait for completion of workflow B.
    • The ExpectNotice Instruction can be used immediately after use of the AddOrder Instruction.
    • The ExpectNotice Instruction can be used at any later node in workflow A.


When clicking Clicking the AddOrder Instruction is used to select the workflow can be selected to which an order should be added for:

  • This includes to specify specifying arguments that should are be added to the ordersorder.
  • Argument names are suggested from according to the declaration of variables declared in the target workflow.
  • Argument values can be specified from with constant values and from using variables that are available with the current order.

First You need to upload the example from the below chapter Workflow B to section below before you will be able to select the relevant Workflow like this:

...

The ExpectNotice Instruction allows to select a Notice Board to be selected.

First You need to upload the example from the below chapter the Notice Board to section below before you will be able to select the relevant Notice Board like this:

...

  • The workflow executes a number of jobs and a JS7 - PostNotice PostNotices Instruction.
  • The PostNotice Instruction sends a signal to any workflows expecting the Notice.
    • A number of workflows can wait for the same Notice of from PostNotice Instruction.
    • The same Notice from a PostNotice Instruction can be issued by any number of workflows.
    • The PostNotice Instruction does not necessarily have to be used as the last instruction in a workflow. In fact it can be used at any position in the workflow.

...

The PostNotice Instruction allows to select a Notice Board to be selected.

First You need to upload the example from the below chapter the Notice Board to section below before you will be able to select the relevant Notice Board like this:

...

  • The Notice Board specifies the same rule used to match the expecting order from the ExpectNotice Instruction in workflow A and the posting order of the PostNotice Instruction in workflow B.
  • The selected rule Matching Daily Plan Date rule specifies that both orders of for workflow A and B have to be in scope of the same Daily Plan date.
    • It is a frequently used rule to match for only matching orders only that are have been created for the same date.
    • The Notice Board offers to allows the use of more complex rules, for example to match , matching the Daily Plan date and the order names that can be specified when adding orders.
  • The A Notice is assigned a lifetime. The expecting order in workflow A should pass its ExpectNotice Instruction node within the lifetime of the Notice.
  • Users have the option to of manually add adding Notices from the Resources->Notice Boards view and they can delete Notices from the same view.
  • Find details from You will find further details in the JS7 - Notice Boards article.