Inspecting the Configuration with the Daily Plan

The Job Chains view provides a starting point for showing how the configuration described above comes together. In the screenshot below shows that the Next Start date for the order_cs Order (partly obscured) is now displayed. Now open the Show Daily Plan item in the menu for the order_cs Order can be used to show how the configuration described above comes togetheras shown in the screenshot:

Image Modified

The screenshot shows the Monthly view for December 2017, with Christmas and Boxing Day (2nd Christmas Day) holidays clearly indicated:

Image Modified

The next screenshot shows the Yearly view for 2018:

Image Modified

Easter (Friday, the 30th March and Monday, the 2nd April), for example, is clearly shown as Non-Working Days.

...

Reopen the Set Run-time modal window for the order_cs Order and then click on the + symbol for the Working Day Calendar in the Restrictions column:

Image Modified

This will open the Add Frequency modal window then select the Recurring Days tab Frequency Type as shown in the next screenshot:

Image Modified

After configuring a Recurring Days Frequency for for every 3rd day December 2017 as shown in the screenshot above, repeat this procedure for Every 3rd day for 2018, valid alid from the 1st January to the 31st of December. In both cases the Valid From date sets the point from which every third day is to be counted. Click on Close once both Restrictions have been set. This will return to the Set Run-time window, which will appear as shown in the next screenshot: 

Image Modified

Now click on Submit to save the configuration.

...

The effects of the Every 3rd day Restrictions on execution dates for 2018 can be seen in the Daily Plan view for the order_cs Order shown below:

Image Modified

The regular pattern is only changed when the execution date falls on one of the non-working days specified in the Non-Working Days Calendar. The behavior on Non-Working days was defined for the Order in the Period modal window and described in the Period section above. For both run-times (15:00 and 21:00) the On Non-Working Days setting was left at the default suppress execution.

...

To demonstrate the effects these settings can have on the execution dates, open the Show Run-time modal window for the Order and then click on Edit Period (the pencil symbol), which will open the following window:

Image Modified

Use the select box to change the behavior specified as shown in the screenshot and click on the Save button.

...

The last execution date in 2017 is the Wednesday, 27th of December and the last Working day the 29th. The Note that the execution for Monday, 1st January 2018 will be is not moved to Sunday, the 31st December, as can be seen in the next two screenshots below showing parts of the Daily Plan for 2017 and for 2018 respectively. This is because this date would outside the validity of the Non-Working Day Calendar Frequency, which starts at the 1st January. 

2017

Image Modified

2018

Image Modified

Behavior with Execution after non-working day

With this setting the Order will be executed, for example, on the day after the first of January as shown in the next screenshot without all subsequent days also being moved:

Image Modified

Behavior with "Ignore non-working day"

This setting means, for example, that execution on the 1st of January 2018 will take place as can be seen in the screenshot below:

Image Modified

Mixed Behavior

...